Pathetic Puravankara-Sunshine just an example
Aug 07, 2007 06:51 PM
9001 views
(Updated Aug 09, 2007 11:49 PM)
Product Implementation Rate:
"Buying flat is a
dream for many, investment for some;Selling flats is
business for many, way of cheating for some."
Recent real
estate boom would have tempted many of you to be part of one or the other
category. This article is written and broadcasted to many as part of anti-Purva
campaign. This is written not only to educate to stay away from these
rogues but also as an attempt to tell how pathetically this 420 company
has looted money in name of Purva Sunshine project situated on **Sarjapur road,
Bangalore**.“Purva Sunshine” was one of some
15 projects launched by these rogues called Puravankara. Some of the projects
executed by this company based on Ulasoor road, Bangalore got completed as they were
outsourced to L&T.However several other projects, for that matter off late
all projects went into complete mess due to lack of foresight, business acumen, immaturity and arrogance shown by its MD Gireesh Puravankara.
Being launched in 2004, Purva Sunshine, still stands incomplete on Sarjapur Road as a proof of
lack of commitment by management When this project was launched Purva charged at
least 20% more than surrounding flats.The promised date of delivery was August
- Right from the day one, Purva Sunshine was in soup.For premium which was
paid to these rascals, one would have expected a little maturity in executing
the project.As the MD himself was negligent, no wonder his subordinates hardly
showed any interest towards the project.If at all they were committed then it
was only for demanding installment amount, without showing progress on project.
Their
crookedness came to fore from the day of signing application for an apartment.
This is even before signing construction and sale agreements.The shameless
fellow YN Rao who handles After Sales department started telling for any delay
one has to pay the penalty. While begging like this these thugs should have
known, on their part there should not be any delay in bringing up project.
Within 8 months
of launch Purva Sunshine, construction came to a complete halt. Obviously
anxious investors wanted to meet the After Sales department headed by YN Rao.
This fellow started telling he is unaware of any happenings and he has not got
any feedback from Engineering department. Incidentally it must be noted that this
YN Rao is only contact person for all flats and all projects of Purva. So no
wonder, his mobile always remained off. Yes, there are two more buffoons in the
ring. One Sankarnarayanan and other Naina who are from public relations and
marketing departments respectively. These people are also good for nothing for
the fact that they don’t even know what happens at site.
Inspite of
sending several mails, memos and making phone calls management never bothered
to come forward and address its customers. So in a nutshell, there was no one
to inform why project is stopped. Finally good number of buyers of Sunshine
barged into office and demanded MD Gireesh Puravankara to come forward and
address. This insensitive MD did not even bother to come and listen. When he
realized that people are not going to move out he had no way but to come and
address.Following were his excuses...1.It rained heavily in Bangalore and hence construction got
delayed. (2)BDA asked him to stop and relinquish part of land
because of proposed peripheral ring road.(3)The village panchayat threatened workers because
village was getting disturbed at night.
However he
said, Purva is committed to complete work within 2 months. He was assuring this
when all floors were not even in near sight.
It did not take
much time for people to realize inside story. When BDA asked Purva to
relinquish part of land, Purva’s after sales office sold some of the flats
which were supposed to belong to landlord Nagaraj Reddy to other customers.
This guy brought the work to a halt demanding for his flats. However Purva
management never bothered to convey message to investors that they had to give
away substantial land and instead of that they got approval from BDA to
construct 2 more floors. Purvankara sold these extra flats at much higher rates
to new customers.
After multiple vociferous
meetings also construction never proceeded. During one of such meetings Gireesh
Puravankara said, the contractor has ditched him. Now Purva has to build with
its own resources. At no point of time one could see more than 20 people
working on this large project which had around 250 flats.As this senseless MD
kept telling he has quality workers and kept committing vague dates, everyone had
understood that he has no sense of what business he is into. Many a times he
even went on to say project is almost completed whereas nothing was there at
site. To overcome such meaningless talk, he was asked to come to site for
meetings. Though he agreed to come, he stayed away from on site meetings,
quoting that he had more urgent work to do. During one of the meetings held at
office, he introduced two more buffoons- Subhan and Suhas Kulkarni who
maintained safe distance all the time from project and people who had concerns.
If one person kept his mobile off, other one always said either he was in Delhi or Dubai
and he has lots of other issues to look at.Each department of this company has
shown no concern to customers beyond Marketing. Modification department headed
by Maregowda does not even bother to inform about consequences of
modifications.
However their charges are sky high and once you make payment
they will not even bother to address your queries. For shifting an electric
point they charge Rs.1800/ . To put a water tap it costs Rs.7000/-
Though in this
article Purva Sunshine has been mentioned, the facts hold good with any Purva
project as same people handle all projects here.Several projects which they
say that they have completed are actually incomplete.For Purva Sunshine,
though management may say, many have taken possessions, not even one has done
that happily.They have taken mainly because though the project is not in a
livable state, even after 1 year delay, Puravankara has not paid late penalty.
On the other side, many lived in rented houses where they had to pay the rent
as well.The unrealistic and impractical dates given by Purva made many people
to take admissions in schools around Sarjapur road.So they had no way but to
move in while construction is still in progress.The worst part of Purva is
that they kept on blaming contractors, cement prices, rain, local panchayat, land
lord etc.Whereas the fact is they never had capacity to build such a building.Today problems galore at site; many flats which Puravankara claims are complete
have un-leveled tiles, water gushes in, doors and windows don’t fit and lifts
not working.Walk into this Purva Sunshine even today, you will not see more
than 25 workers who do everything right from tiling, painting, septic
tank, electric fitting to compound wall.It has been 3 years since this project
got launched.No one here at site, has any prior experience in construction.Above all Gireesh
Puravankara says this is one of his best quality projects.This shows how much
he understands quality and how much of ground realities he is familiar with.
This Pathetic Puravankara is not
something on which you can count.These are not guys worth your time or money.
-
-
Thank You! We appreciate your effort.
Upload photo files with .jpg, .png and .gif extensions. Image size per photo cannot exceed 10 MB
Brand Response
Dear Customer,
Greetings from Puravankara!
This mail is to keep you informed that we have read the review you have posted in www.mouthshut.com about your experience with us.
We sincerely regret the inconvenience caused to you.
We at Puravankara would like to address your concerns as soon as possible and hence request you to kindly share your contact details along with Project name & apartment number with us.
Looking forward to hear from you soon.
Warm regards
Team Puravankara
By: Puravankara_Corp | May 30, 2014 03:30 PM