I'm Owner of a flat at Puravankara Panorama when I booked in early 2005 I was really very happy that I booked my "Dream House" with a organization which has name which is commited and they have Quality as well.
I won't say that i'm 100% satisfied but ofcourse i'm satisfied with the construction quality, finishing and other work, of course there was more scope of doing the things better but still I'm okie with and in future if i've to take another home i'll look back to Purvankara Project.
Yes its true possession is delayed especially for Phase I people its more than 06 months delay but this is the case by every builder and in every town and when I booked in 2005 I was 200% sure that project will be delayed by few months .Not big deal for such huge project, Same is true with builders like Brigade & Mantri. We need to understand that builders are also dependent upon labours and imagine now a days its difficult to find manforce.
I personally feel that If Purvankara people / official were not that bad and we should not critice so much after all they are also human, If we have booked a flat then these tension are bound to come but I will appriciate people like Sankar Narayan, Y N Rao, Deepak, Site people that they have always helped me and were always available. Thanks to all the people of Purvankara.
Panorama project is under litigation and I would like to state that Purvankara people are issuing letter to all owners, and this is not New in bangalore. Project took good 3 years to complete were these SC/ST people were sleeping why did they not claimed earlier, Why did they not put notice earlier, They only realised now, moreover this project is approved by BDA, All leading financial instituation have approved this project moreover registration has happend in two BDA office(Kormangala & Begur), KPTCL connection has come, So in worst case its not only 600 people who are involved but all these institution is also involved. Mind you Panorama is not going to nbe the last Project by Puravankara IF PURVANKARA PROJECTS PVT LTD want to survive in the real estate market then i'm very sure they will do there best.
I must agree that now work is going at full speed, All internal road has come up, Club House work is going on, they have started procuring equipements for club house and so on, and I guess by Mid October we should see Club house functioning, Landscape work is going on and with in october that should also be completed. We are concerned regd Size of swiming pool and store, only 1 TT table is alloted and so on, As a customer when we booked Panorama have we ever tried to get these details regd the size and all, Moreover Panorama is no where mentioned as Luxuary Apartment, We shoul;d have raised our concerns regd size and amenities long back not now, moreover I feel that no documents(Construction / Sale) talks about the same so Purvankara is not bound to accept our demands, however I fully agree that a soceity which has 600+ flats should have a bigger swiming pool and amenties and we can still request for same.
Issues like water / leakeage and all are being handled by concerned authority and I think it will be
resolved within few weeks. KPTCL power has come in July end, similarly BWSSB is expected to come with in a month or so.
There are issues regd Delay possession amount if yopu read the construction agreement carefully then there are two points which we need to look for. 1. Is by any chance our PAYMENT IS DELAYED(I'm sure for many it is) 2. Due to unforseen situations project can be delayed(I'm sure in past 3 years in bangalore didn't experienced and such issues) But except for people who went for Upfront payment most of the people have delayed the payment so as per agreement i'll rather say Puravankara is doing right.
So guys lets be constructive and help puravankara people for smooth finish of the project, Lets not criticise our own apartment, our own investment. Think what impact we are making about our flat to outside soceity.
So I request all if there are issues we can resolve with Purvankara people. Would like to thaks to all at Purvankara projects for all there help and support.
-
-