Positive note for new investors
Jul 09, 2012 09:53 AM
17905 views
Product Implementation Rate:
This note is for the new buyers of Manjeera Diamond Towers:
I have a friend's father who's the VP of Manjeera Constructions. I wanted to purchase a flat in Manjeera, so I went up to him with these negative comments.
PFB the response given by him:
1) TCS hostel issue : To maintain the brand value of Manjeera, 3 towers were given to TCS new joinees on agreement with flat owners, which was considered as a smart move during recession times.But, it turned out to be an issue for the other residents.The tenure for TCS employees is going to get completed in 2 years.Which will surely resolve the issue.
2) Delay in construction : Construction started parallel in 8 towers and due too recession, the number of takers fell down drastically and the count at that time was 150/700, where the 150 homes were spread out across various towers.So lack of insufficient funds lead to delay.Now, just 20% of flats are available, which ensures more than sufficient funding for successful completion of the project with minimal delay.
3) Amenities and facilities : Facilities and amenities will be provided as promised and the greenery would be maintained.Construction of the club house has already been started.
I am not denying the fact that negative comments were wrong.All those negative comments would be very positively answered.
The current price quoted is a very good deal considering the proximity of the location.
Think wise before taking a step and make sure that you don't lose a good deal because of the above factors.
I have booked a flat yesterday and hope to get it ready by March, 2012.
Also, I would like to list down some positives of the project.
Intimation of continuous progress :The continuous progress of the project would be updated to the buyers on regular basis through text mails and videos which every investor has to agree.
Happy investor : Every person who chose this project is happy as an investor.
EMI payment : The management was paying regular Pre EMIs even though there was delay in the project which every investor has to agree.
-
-
Thank You! We appreciate your effort.