No for Mahaveer, especially under construction.
Nov 10, 2015 06:43 PM
71248 views
(Updated Feb 06, 2016 02:21 PM)
Product Implementation Rate:
I booked a flat in Mahaveer 3 years back, which I will call as the biggest mistake of my life.
I want none of you to face the same problem I went through.
I sold the flat, to regain my peace of mind.
Explaining the struggle I gone through.
I had to pay EMI of 25k for 1.8 years along with house rent. Since they delayed the project for 1.8 years after the promised end date.  [Actual delay was around 3.5 years for those who booked the flat before me].
Very poor planning of the project.
a. In the project where I got the flat, they kept 400V electric board in front of some flats with a danger symbol. Think about your kid going near the control board.
b. Transformer was just near other few flats.
c. The entrance to the parking(in basement) was very narrow. Residents were facing problem in entry or exit.
d. Fire engine or a little bigger vehicle than a normal car cannot enter the apartment. Safety aspect was very bad.
- Management/ People.
a. Until they took the money from me, marketing manager was very polite and gentle, once the money went to their pocket, the manager was not picking the call. He started behaving very rudely.
b. Engineer was making several false promises. When a task will take only one day hardly, he was taking 2-4 weeks to complete the work. As though they are doing with their money and giving you the flat for free.
c. When some work was not progressing and when I asked the engineer/ marketing manager, they asked me to contact their manager, then manager's manager until head. But, the problem never solved. I lost hope on mahaveer completely.
- Very poor quality of work.
a. Several deviation from the actual plan. Without bribing, A khata cannot be taken for the apartment.
b. Most of the materials used were of poor quality. I have asked them to change the tiles 3 times(after several reminders).
c.The windows were not moving at all. The doors were not locking properly.
d. I had to pay money to their people itself, to complete the flat work. Several thousands.
e. Plumbing/ Electrical work was also very poor.
- Everyday I had to spend atleast 2-3 hours waiting for the so called labours and engineer. Eventhough they promised me they will come in 10 minutes. My professional life was badly affected, because of them.
I had to commute a lot and I had to shout at these guys for even the smallest work. My health was also badly affected.
I sold the flat to regain my health, professional life, money, peace of mind.
Please take care. Never buy any apartment from Mahaveer or any other 3rd class builder atleast when it is under construction.
Even it is 10-15 costly, wait for some time and buy from good builder.
If you are healthy and have peace of mind, you can do anything in your life.
-
-