KUL ECOLOCH REVIEW
Apr 02, 2015 08:20 PM
26348 views
Product Implementation Rate:
I and many other customers booked flats in KUL ECOLOCH Phase 1 in May-Dec 2011.
My registration was done on Feb 2012 and till now(Apr 2015), we haven't got possession of our flats.
They have completed buildings and flats in order to receive 95% payment in Dec 2013 but they haven't done outside building amenities like road, lights, water, garden, club house till now(Apr 2015). So, obviously we cannot get possession.
Since from Dec 2013, builder is pushing dates of possession and halts progress of development. I am not sure may be he wanted to eat our money for interest and use in another business.
Builder has promised possession of phase 1 on dec 2013 at the time of booking and because of this and Kumar builder's name, I have booked flat there and made biggest mistake of my life.
Its been now 4 years I am chasing them for possession but they are still not giving it.
Now, I have to pay EMI+ House rent together and its overhead.
Also, wash basin and window quality is ridiculous. Wash basin is small and square shaped same like in lodges.
Compare to this builder, there are lot many other good builders in pune. Even, small builders are good than this builder.
I recommend not to buy flats here. If you are thinking for investment and ready to wait 4 years then buy here.