After 18 months delay, and a million follow-ups, I got a bomb shell in the email asking me a penalty of 3.75 lakhs as late payment penalties.
It is the worst cheat I have ever had in my life!
Dont even think of talking to the marketing guys of Purvankara. they fall in your feet to sell the flat and make you lick their feet to get your house!
Builder no where close to answering these questions!
Delivery delayed by 18 months, no compensation has been paid for the delays.
After all these delays, Delivering house is not just the walls and the doors what about completion of the whole
project? According to the builder handover does not cover the fire exit, lift work, reception, park, swimming pool, car parking.
Unfair practices on the penalties 24% for receivables and 6% for payable.
Huge change in the costs of BWSSB, KPTCL which was shown lesser during the buy. Bowling alley was
projected as if it were a amenity. Later on came to know that this is as costly as the Leela palace for a game of bowling It was advertised as ‘World Class Luxury Apartment’, what is their meaning of world class. An enquiry to be done to compare an apartment in Singapore and Elita in Bangalore.
Actual house no where close to model flat (In fact, why did they demolish the model flat as early as
possible? The marketing material and the looks of the apartment is no where close to the actual building in
terms of gardens, lake side apartment, walking lawns, jogging track etc.
Different tiles for different rooms. Cheap granite broken stones in the Kitchen. Very Poor quality doors and fittings